Area Projects priority timeline Specific Needs projected costs projected hours acutal $$ actual hours completion date notes
Las Perlas       $760.00 230        
Project 1 1 Apr-05 $280.00 58
two 1500 L contnrs $140.00 6 $140
lumber shed
roofing $50.00
retrofit tanks 6
transport to cave $50.00 6
build structures 40
misc hardware $40.00
Proj 2 2 Apr-05 $0.00 10
aquire frames from bins
chicken wire own
roofing own???
build structures 4
transport to cave 4
fill with old compost 2
Proj 3 4 Apr-05 $280.00 86
mill lumber 16
build cabinets 20
buy sinks $200.00 4
misc hardware $80.00
transport to cave 6
remodel kitchen 40
Proj 4 3 Apr-05 $100.00 54
dig/line ponds 24
buy plumbing $100.00 6
transport to cave 4
install plumbing 20
Proj 5 6 Jun-05 $100.00 56
design bodega 6
mill wood 6
buy hardware $100.00 4
build bodega 40
Escalaris Campus       $23,870.00 668        
Nursery 4 May-05 $600.00 82
buy trees $500.00 16
buy materials $100.00 20
transport to cave 6
remodel kitchen 40
Water System 3 May-05 $170.00 54
tap spring 24
buy 1500 L tank $70.00 6
buy plumbing $100.00 4
install plumbing 20
Micro Hydro System 6 Jun-05 $5,100.00 62
design system 25
buy materials $5,000.00 12
trnspt to meadow $100.00 10
build bodega 40
Yoga Studio 2 Aug-05 $16,000.00 354
design studio 12
mill lumber own 30
buy supplies $6,000.00 12
build structures $6,000.00 200
trnsprt mat. to cave $1,000.00 50
misc $3,000.00 50
Meditation Hut 5 Sep-05 $2,000.00 116
design structure 12
mill lumber own 12
buy supplies $1,000.00 12
build structures $600.00 50
trnsprt mat. to cave $200.00 10
misc $200.00 20
Farm Preparation 2 Apr-05 $1,600.00 467
buy tools $1,000.00
prepare soil 100
build bodega $500.00 40
horse fence $100.00 20
plant nitrogen fixers 25
plant ground cover 20
plant trees 200
trnsprt mat. to cave 12
misc 50
Next Project 5 Sep-05 $0.00 0
design structure
mill lumber own
buy supplies
build structures
trnsprt mat. to cave
misc
Community Chapel       $5,870.00 198        
Nursery 4 May-05 $600.00 82
buy trees $500.00 16
buy materials $100.00 20
transport to cave 6
remodel kitchen 40
Water System 3 May-05 $170.00 54
tap spring 24
buy 1500 L tank $70.00 6
buy plumbing $100.00 4
install plumbing 20
Micro Hydro System 6 Jun-05 $5,100.00 62
design system 25
buy materials $5,000.00 12
trnspt to meadow $100.00 10
build bodega 40